All of the trees for this project have been planted and the bioswales have been constructed in the parking lot off of Compass Road.
Next week, Plote Construction is scheduled to continue with grading subgrade and construction of the aggregate base course in the parking lot off of Compass Road. Mid-next week, Plote Construction is planning on paving the asphalt base course in the north and south driving lanes and parking stalls of the Compass Road parking lot. Late next week (weather permitting), Plote Construction is scheduled for the first day of pervious concrete placement in the central portion of the Compass Road parking lot.