The project includes the construction of three (3) new commuter parking lots at the Glen-Metra Train Station. Two (2) parking lots will be constructed north and south of the train station off of Lehigh Avenue. One (1) parking lot will be constructed off of Compass Road (west of Lehigh Avenue). Plote Construction Inc. is the general contractor for this project.
Friday, September 30, 2011
Friday, September 23, 2011
Friday, September 16, 2011
Friday, September 9, 2011
Friday, September 2, 2011
Friday, August 26, 2011
Friday, August 19, 2011
All of the trees for this project have been planted and the bioswales have been constructed in the parking lot off of Compass Road.
Next week, Plote Construction is scheduled to continue with grading subgrade and construction of the aggregate base course in the parking lot off of Compass Road. Mid-next week, Plote Construction is planning on paving the asphalt base course in the north and south driving lanes and parking stalls of the Compass Road parking lot. Late next week (weather permitting), Plote Construction is scheduled for the first day of pervious concrete placement in the central portion of the Compass Road parking lot.
Next week, Plote Construction is scheduled to continue with grading subgrade and construction of the aggregate base course in the parking lot off of Compass Road. Mid-next week, Plote Construction is planning on paving the asphalt base course in the north and south driving lanes and parking stalls of the Compass Road parking lot. Late next week (weather permitting), Plote Construction is scheduled for the first day of pervious concrete placement in the central portion of the Compass Road parking lot.